Task Estimation
Enter optimistic, most likely, and pessimistic time estimates for your task.
PERT Estimates
Best-case scenario
Most realistic
Worst-case scenario
Expected Time
4.3
hours
Std Deviation
1.0
hours
68% Range
3.3 - 5.3
hours
95% Range
2.3 - 6.3
hours
Distribution
Best Case
1.3 hours
Expected
4.3 hours
Worst Case
7.3 hours
Confidence Intervals
68% confidence~1σ
Most likely outcome range3.35.3hours
95% confidence~2σ
High confidence range2.36.3hours
99.7% confidence~3σ
Maximum range1.37.3hours
How PERT Works
Expected Time: Calculated as (O + 4M + P) / 6, giving more weight to the most likely estimate.
Standard Deviation: Measures uncertainty, calculated as (P - O) / 6.
Confidence Intervals: Statistical ranges showing probability of completion within timeframes:
- 68% confidence (±1σ): Most likely outcome range
- 95% confidence (±2σ): High probability range
- 99.7% confidence (±3σ): Nearly certain range